#11 Return to GC's Project Schedule - Lead Time - Submitals - Delivery

Identify off-site tasks;

Subcontractors;
-scope of work
-negotiate subcontract
-availability
-equipment to be supplied by GC
-materials to be supplied by GC

GC workforce;
-trades required for tasks, scope of task
-trades available within GC's permanent workforce
-trades to be hired for task, for project

GC equipment;
-equipment required for tasks
-equipment available within GC's stable
-equipment to be rented/leased
-equipment to be purchased
-fuel and service equipment during project

Materials;
-materials required for tasks
-identify GC or subcontractor supply
-identify sources
-negotiate cost, deliver or GC pick-up
-identify submital requirement and approval schedule

Components
-components installation tasks
-workforce and equipment requirements
-submital and approval schedule
-negotiate cost, deliver, or GC pick-up

Clean-up

-GC workforce required for general site mantainance and periodic clean-up

Example;

Off site arrangements for task; Metal light pole system;

Subcontractors;
-Rigger
-Excavator
-Concrete Sub
-Electrician

Equipment;
-Boom truck by rigger
-Auger and trencher by excavator
-Bucket truck by electrician

Materials;
-Concrete; order and pay ready mix by concrete subcontractor
-tube form; supply and install by concrete subcontractor
-reinforcing cage; supply and install by concrete subcontractor
-conduit and cable; supply and install by electrical subcontractor
-PA 2B or stone dust cable trench fill by excavation subcontractor
-crushed stone base for concrete by excavation subcontractor

On site inspections
-3rd party engineer inspections by GC's testing subcontractor
-Local building inspector, call inspection request by GC's site supervisor

On site layout including elevation reference
-Layout survey crew by GC's survey consultant

Components -Metal Light Pole
-Negotiate price, delivery and ordered by GC
-Setting plate for top of concrete base (set by concrete sub from reference by layout crew)
-Light pole (rigger install, electrician wire)
-Light fixtures (rigger hang fixture, electrician wire and install lamp)


Assignment; for Wednesday;
MS Project insert lead time; submital, order and delivery for light poles as a sub element under light poles.
You may negotiate with subs and suppliers before notice to proceed but probably not have a contract with subs or place order for components until order to proceed is issued.


Coming next:

#12 Project Schedule Cash flow predictions

Final assignment due Sunday August 9 not later than midnight;


Introduce a change order for wood light poles assume approved for voucher period #2

Revise schedule of values, MS Project Schedule and multi line graph, Discuss how this change impacts the GC and the Owner.

No comments:

Post a Comment

Construction Management 2

CM2 will focus on scheduling, quanitity take-off and construction cost estimating from the perspective of the General Contractor.

Scheduling using MS Project 2007;
Current editions of MS Office Professional edition contain MS Project 2007.
MS Project 2007 is also available on some computers in the A&D building, check with PhilaU OIT for access.

Quantity Take-Off;
We will be using full size drawing, for the take-off section including; cut and fill calculations, stormwater management and environmental remediation.

Construction Cost Estimating;
Information from the quantity take-off will be used for construction cost estimating using "National Construction Estimator 2007 from Craftsman"

Project Cash Flow;
Data from the cost estimating program with overhead and profit factors will be used with the Schedule to inform cash flow, line of credit, gross profit and net profit.

Review impact of project delay from; owner, arch/eng, GC, regulatory, weather, industrial action,....

Review impact of project change order on cash flow and overhead and profit.