Subcontractors;
-scope of work
-negotiate subcontract
-availability
-equipment to be supplied by GC
-materials to be supplied by GC
GC workforce;
-trades required for tasks, scope of task
-trades available within GC's permanent workforce
-trades to be hired for task, for project
GC equipment;
-equipment required for tasks
-equipment available within GC's stable
-equipment to be rented/leased
-equipment to be purchased
-fuel and service equipment during project
Materials;
-materials required for tasks
-identify GC or subcontractor supply
-identify sources
-negotiate cost, deliver or GC pick-up
-identify submital requirement and approval schedule
Components
-components installation tasks
-workforce and equipment requirements
-submital and approval schedule
-negotiate cost, deliver, or GC pick-up
Clean-up
-GC workforce required for general site mantainance and periodic clean-up
Example;
Off site arrangements for task; Metal light pole system;Subcontractors;
-Rigger
-Excavator
-Concrete Sub
-Electrician
Equipment;
-Boom truck by rigger
-Auger and trencher by excavator
-Bucket truck by electrician
Materials;
-Concrete; order and pay ready mix by concrete subcontractor
-tube form; supply and install by concrete subcontractor
-reinforcing cage; supply and install by concrete subcontractor
-conduit and cable; supply and install by electrical subcontractor
-PA 2B or stone dust cable trench fill by excavation subcontractor
-crushed stone base for concrete by excavation subcontractor
On site inspections
-3rd party engineer inspections by GC's testing subcontractor
-Local building inspector, call inspection request by GC's site supervisor
On site layout including elevation reference
-Layout survey crew by GC's survey consultant
Components -Metal Light Pole
-Negotiate price, delivery and ordered by GC
-Setting plate for top of concrete base (set by concrete sub from reference by layout crew)
-Light pole (rigger install, electrician wire)
-Light fixtures (rigger hang fixture, electrician wire and install lamp)
Assignment; for Wednesday;
MS Project insert lead time; submital, order and delivery for light poles as a sub element under light poles.
You may negotiate with subs and suppliers before notice to proceed but probably not have a contract with subs or place order for components until order to proceed is issued.
Coming next:
#12 Project Schedule Cash flow predictions
Final assignment due Sunday August 9 not later than midnight;
Introduce a change order for wood light poles assume approved for voucher period #2
Revise schedule of values, MS Project Schedule and multi line graph, Discuss how this change impacts the GC and the Owner.